NEW QUESTION 69
What structure level do you see when you access the Roadmap Viewer and chose work stream navigation? Please choose the correct answer.

  • A. Deliverable
  • B. Task
  • C. Scenario
  • D. Scope Item

Answer: A

 

NEW QUESTION 70
Which of the following is a key characteristic of the Agile project approach?

  • A. Iterative build with frequent inspections
  • B. Frequent and detailed project scheduling
  • C. Frequent quality gates
  • D. Formal and detailed documentation

Answer: A

 

NEW QUESTION 71
What is the most granular level of the methodology you can view in the SAP roadmap viewer?

  • A. Deliverables
  • B. Task
  • C. Scenario
  • D. Phase

Answer: B

 

NEW QUESTION 72
In which phase do you create "an ordered list of everything that is known to be needed in the Product?

  • A. Explore
  • B. Deploy
  • C. Prepare
  • D. Realize

Answer: D

 

NEW QUESTION 73
Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool? There are 3 answers to this question.

  • A. System consolidation
  • B. System upgrade
  • C. Consolidation through online data replication
  • D. Security migration
  • E. Extraction of business units

Answer: A,C,E

 

NEW QUESTION 74
Which of the following is a key characteristic of the Agile project approach?

  • A. Iterative build with frequent inspections
  • B. Frequent and detailed project scheduling
  • C. Frequesnt quality gates
  • D. Formal and detailed documentation

Answer: A

 

NEW QUESTION 75
What are the core capabilities in SAP Cloud ALM for implementation? Note: There are 3 correct Answers to this question.

  • A. Custom code management
  • B. Process management
  • C. Task management
  • D. Portfolio management
  • E. Test management

Answer: B,C,E

 

NEW QUESTION 76
What are two important approaches, based on the Control Center concept that SAP proposes to use for streamlined implementation and operations within Premium Engagements? There are 2 correct answers to this question.

  • A. Always Connected
  • B. Intelligent Enterprise
  • C. Run SAP Like a Factory
  • D. Build SAP Like a Factory

Answer: C,D

 

NEW QUESTION 77
What are the enablement areas relevant for all Customer Team members coming from the Business?

  • A. Technical expertise
  • B. Project management
  • C. Solution expertise
  • D. Workstream enablement

Answer: A,B,C

 

NEW QUESTION 78
Which new role is introduced in the SAP activate methodology in a full scrum team?

  • A. Product owner
  • B. Project manager
  • C. System administrator
  • D. Application consultant

Answer: A

 

NEW QUESTION 79
Which artifacts are part of the Solution Adoption workstream? Note: There are 3 correct Answers to this question.

  • A. Project Plan
  • B. Change Management Roadmap
  • C. End User Learning Needs Analysis
  • D. Detailed Design - Business Process
  • E. Learning Content

Answer: B,C,E

 

NEW QUESTION 80
What are some goals of the Fit-to-Standard workshops?

  • A. To gather input for customer-defined customizations to the solution.
  • B. To identify customer-defined configuration changes within the scope of the service.
  • C. To define the Integration and API List for the solution.
  • D. To review the SAP Best Practices in the starter system.
  • E. To identify relevant data migration objects.

Answer: A,B,D

 

NEW QUESTION 81
Which key deliverable includes the development of RICEFW objects? Please choose the correct answer. Response:

  • A. Custom Extensions Management
  • B. Enhancement Delivery
  • C. Sprint Execution
  • D. Development Build

Answer: B

 

NEW QUESTION 82
What is the primary function of the Starter System in the Fit-to-Standard workshops?

  • A. To gather the customer's detailed configuration requirements
  • B. To provide a secondary sandbox that will be maintained by the customer post go-live
  • C. To demonstrate SAP Best Practices
  • D. To configure and test the solution in a sandbox

Answer: C

 

NEW QUESTION 83
What is the objective of a Sprint Retrospective meeting?

  • A. Review and prioritize the backlog.
  • B. Improve the Scrum process.
  • C. Provide formal feedback to the project manager.
  • D. Define the stakeholder management approach.

Answer: B

 

NEW QUESTION 84
What is the term used for workshops, which are intended to set value targets, validate SAP Standard functionality against customer requirements.
And collect delta requirements in the "New Implementation of SAP S/4HANA" transition path?

  • A. Delta Design
  • B. Fit-to-Standard
  • C. Solution Validation
  • D. Design Thinking

Answer: C

 

NEW QUESTION 85
When does the Scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?

  • A. During the daily Scrum meeting
  • B. During the user acceptance test
  • C. During the Sprint Review
  • D. During the Sprint Retrospective

Answer: C

 

NEW QUESTION 86
Which of the following are the benefits of SAP JAM? There are 2 answers to this question.

  • A. Highly available
  • B. Easy to use
  • C. User collaboration
  • D. Reduced Recovery Time

Answer: B,C

 

NEW QUESTION 87
Via which media does SAP provide ready-to-run systems for SAP S/4HANA deployment? There are 2 answers to this question.

  • A. SAP App centre
  • B. Blu-ray disks
  • C. SAP cloud appliance library
  • D. SAP Solution Builder tool

Answer: B,C

 

NEW QUESTION 88
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?

  • A. Go-Live scope is fixed on the first of January the following year.
  • B. Project scope and planning are completed and final.
  • C. User Stories are in Ready state for only the first 2 to 3 sprints.
  • D. Timelines of the sprint may differ due to the workload.

Answer: C

 