NEW QUESTION 40
A critical issue has developed in an active project, and the project manager wants to notify the 20-person global project manager use FIRST to relay this information?
- A. Send an email to all project team members.
- B. Individually call all project team members.
- C. Schedule a face-to-face meeting.
- D. Schedule a conference call.
Answer: D
NEW QUESTION 41
A project manager needs to identify the resources assigned to a particular task.
In which of the following documents can this information be found?
- A. Scope statement
- B. Impact assessment
- C. Project schedule
- D. Cost plan
Answer: C
Explanation:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 156
NEW QUESTION 42
A member of a CCB notices a change request was not approved by the steering committee. Which of the following is the BEST method to handle this situation?
- A. Develop a regression plan.
- B. Disapprove the change request.
- C. Hold the change request for review
- D. Evaluate the impact of the change.
Answer: D
NEW QUESTION 43
Which of the following can a project manager use to keep track of finances and ensure costs are accurately applied to a project?
- A. Bill of materials
- B. WBS codes
- C. Cost baseline
- D. PO numbers
Answer: B
NEW QUESTION 44
Which of the following events would MOST likely trigger communications to the largest audience for a given organization?
- A. Business continuity response
- B. Replacement of a subcontractor
- C. Quality audit
- D. Completion of a task
Answer: A
Explanation:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 273
NEW QUESTION 45
Which of the following is a key aspect of the Agile project management methodology?
- A. Short project durations
- B. Daily standup meetings
- C. Defined list of requirements
- D. Test-driven
Answer: B
Explanation:
References:
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 286
NEW QUESTION 46
During the execution phase of a project, a project task has run longer than anticipated.
Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
- A. 12 days
- B. 19 days
- C. 16 days
- D. 14 days
Answer: A
Explanation:
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 169
NEW QUESTION 47
A project team is not delivering their tasks in a timely manner. Additionally, tasks are being reworked because requirements continue to be identified as work packages are being delivered.
Which of the following are MOST likely missing from the project? (Choose two.)
- A. Status report
- B. Scope document
- C. Business case
- D. Organizational chart
- E. Project charter
- F. Project plan
Answer: B,F
NEW QUESTION 48
A project manager who is part of a global team wants to have a team building meeting and decides to hold a video conference.
Which of the following is MOST likely to be the main challenge the influences this decision?
- A. Cultural differences
- B. Language barriers
- C. Geographical factors
- D. Technology factors
Answer: C
Explanation:
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 259
NEW QUESTION 49
Which of the following is the primary purpose of an MOA or an MOU?
- A. Enumerate a detailed code of conduct for all employees, contractors, and subcontractors participating in the program.
- B. Facilitate potential legal action and resulting remediation if one of the signatory parties violates any terms.
- C. Provide transparency to competitors regarding all signatory parties.
- D. State expectations of all signatory parties to reduce potential misunderstandings.
Answer: D
Explanation:
Explanation/Reference: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 303
NEW QUESTION 50
Which of the following is a schedule that illustrates the duration of an activity?
- A. Gantt chart
- B. Pareto chart
- C. Process diagram
- D. Ishikawa diagram
Answer: A
Explanation:
References:
Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 168
NEW QUESTION 51
Task A starts on Day 1 and has a duration of two days. Task B has a duration of two days and starts on Day 3.
Task C starts after Task A and has a duration of three days. Task D starts after Task B and Task C and has a duration of one day. Which of the following represents the critical path?
- A. Eight days
- B. Five days
- C. Seven days
- D. Six days
Answer: D
NEW QUESTION 52
During the risk assessment process, the qualitative analysis results in the majority of risk scores being rated as medium.
Which of the following is the BEST course of action?
- A. Add the risks to the watch list.
- B. Assign the sponsor as the primary risk owner.
- C. Increase the contingency reserve.
- D. Establish and monitor trigger conditions.
Answer: D
NEW QUESTION 53
An organization has determined that all projects must use a remote dashboard to allow portfolio management.
Which of the following would enforce this directive?
- A. Project coordinator
- B. Project manager
- C. Project sponsor
- D. Project management office
Answer: D
NEW QUESTION 54
A customer has requested additional features for an active project.
Which of the following steps should take place NEXT?
- A. Evaluate the impact of the changes.
- B. Implement the requested changes.
- C. Update all project documents.
- D. Submit the requested changes to the CCB.
Answer: A
Explanation:
Explanation/Reference:
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 293
NEW QUESTION 55
Which of the following statements are correct regarding project management? (Choose two.)
- A. An organization's portfolio is a temporary and unique endeavor.
- B. A program has a defined start and finish.
- C. An organization's portfolio will include programs.
- D. A project can be part of an organization's program management.
- E. A project portfolio will be managed under program management.
Answer: B,C
NEW QUESTION 56
A project manager travels abroad to meet the offshore team and sends out a meeting invitation to review requirements. However, many team members decline the meeting invitation. The PM approaches one team member to determine why people are declining. The team member indicates the project manager scheduled the meeting at a time when employees typically have permission to take a nap. Which of the following is the project manager facing?
- A. Personal preferences
- B. Language barriers
- C. Time zones
- D. Cultural differences
Answer: D
NEW QUESTION 57
Which of the following are characteristics of qualitative risk assessments as opposed to quantitative? (Choose two.)
- A. Qualitative assessments better identify opportunities.
- B. Qualitative assessments provide more accurate results.
- C. Qualitative assessments are faster.
- D. Qualitative assessments are more difficult.
- E. Qualitative assessments require fewer resources.
Answer: C,E
NEW QUESTION 58
Two team members are arguing over two different approaches to complete a task. The project manager listens to both sides, determines neither approach will work, and directs the team members to use a third option.
This type of conflict resolution is known as:
- A. forcing.
- B. compromising.
- C. avoiding.
- D. smoothing.
Answer: A
Explanation:
Explanation
References: Kim Heldman, CompTIA Project+ Study Guide, 2nd Edition, Sybex, Indianapolis, 2017, p. 200
NEW QUESTION 59
......
PK0-004 exam questions from Pass4training dumps: https://www.pass4training.com/PK0-004-pass-exam-training.html (571 Q&As)
Free 2021 Project+ PK0-004 dumps are available on Google Drive shared by Pass4training: https://drive.google.com/open?id=1Zv4Mr2U52ILYKs5J9bJrruWK3xLDTvfS