PRINCE2 (PRojects IN Controlled Environments) is a widely recognized and highly valued project management methodology that is used worldwide. The PRINCE2 methodology is designed to provide a structured approach to project management, allowing organizations to deliver projects on time, within budget, and to the required quality. The PRINCE2 methodology is built on seven principles, seven themes, and seven processes. PRINCE2 Foundation certification is an entry-level certification that provides an understanding of the PRINCE2 methodology and its application in project management.

 

NEW QUESTION # 133
Which process provides the Project Board with sufficient information for it to review the success of a completed stage and confirm continued business justification?

  • A. Closing a Project
  • B. Directing a Project
  • C. Managing a Stage Boundary
  • D. Controlling a Stage

Answer: C

Explanation:
Section: Volume B


NEW QUESTION # 134
According to the 'defined roles and responsibilities' principle, how many categories of stakeholder interest need to be represented in the project management team?

  • A. Three
  • B. Six
  • C. One
  • D. Two

Answer: A

Explanation:
According to the 'defined roles and responsibilities' principle in PRINCE2, three categories of stakeholder interest need to be represented in the project management team: business (represented by the Executive), user (represented by the Senior User), and supplier (represented by the Senior Supplier). This ensures that the key perspectives on the project's outputs, outcomes, and processes are fully integrated into decision-making and governance structures.References: PRINCE2 Foundation ManualAccording to the 'defined roles and responsibilities' principle in PRINCE2, three categories of stakeholder interest need to be represented in the project management team: business (represented by the Executive), user (represented by the Senior User), and supplier (represented by the Senior Supplier). This ensures that the key perspectives on the project's outputs, outcomes, and processes are fully integrated into decision-making and governance structures.References: PRINCE2 Foundation Manual


NEW QUESTION # 135
Where should a Team Manager look for information on the quality required for a product?

  • A. Product Description
  • B. Quality Management Strategy
  • C. Project Initiation Documentation
  • D. Team Plan

Answer: A


NEW QUESTION # 136
Which is a description of a purpose of the communication management approach?

  • A. To document for stakeholders the future business required to meet project objectives
  • B. To document the responsibilities of project team members for testing whether products are acceptable to users
  • C. To document how to use financial incentives to motivate project team members
  • D. To document how the project team should control its interactions with stakeholders

Answer: D

Explanation:
The purpose of the 'communication management approach' is to document how the project team will control and manage its interactions with stakeholders. This includes detailing the methods and frequency of communication to ensure all parties are appropriately informed and engaged throughout the project lifecycle.References: PRINCE2 7 Foundation guide on communication management.


NEW QUESTION # 137
Which is a purpose of the business case theme?

  • A. To identify the project's outputs
  • B. To identify which role is responsible for producing the business case
  • C. To establish the controls to manage changes that may impact the project benefits
  • D. To establish a viable investment proposition

Answer: A

Explanation:
Section: Volume B
Explanation/Reference:
Reference http://prince2.wiki/Business_Case


NEW QUESTION # 138
The benefits Management approach has been reviewed by the project board to ensure there are sufficient benefit reviews after the project has closed.
Which principle is the project board applying?

  • A. Manage by stages
  • B. Focus on products
  • C. Ensure continued business Justification
  • D. Manage by exception

Answer: C

Explanation:
The principle of 'Ensure continued business justification' in PRINCE2requires that the project remains justified throughout its lifecycle. By reviewing the benefits management approach to ensure it includes sufficient benefit reviews after the project's closure, the project board is applying this principle to confirm that the project continues to provide value and that its benefits are realized as planned, even post-project.
References: = PRINCE27 Foundation Training Manual and official PRINCE2website documentation


NEW QUESTION # 139
Which is a purpose of an End Project Report?

  • A. Identify individuals or groups that are responsible for measuring the expected benefits after the project has closed
  • B. Identify individuals or groups that need to be told that the project is coming to an end
  • C. Review how well the project performed against the Project Initiation Documentation used to authorize it
  • D. Ensure that key project information is archived and made secure

Answer: C


NEW QUESTION # 140
What theme estimates the cost of delivering the project?

  • A. Plans
  • B. Change
  • C. Progress
  • D. Business Case

Answer: A


NEW QUESTION # 141
Why is it necessary to apply the 'defined roles and responsibilities' principle?

  • A. Because the project management team should be cross-functional
  • B. Because the project manager should represent all the stakeholders of the project
  • C. Because the people involved in a project should know what is expected of them
  • D. Because the user and supplier interests should be involved on a need-to-know basis

Answer: C

Explanation:
Section: Volume B


NEW QUESTION # 142
Which is a task of product-based planning?

  • A. Prepare the Work Packages
  • B. Identify activities and dependencies
  • C. Write the Project Product Description
  • D. Produce Product Status Accounts

Answer: C

Explanation:
A task of product-based planning in PRINCE2 is to write the Project Product Description. This is part of defining and documenting the project's output, outcome, and benefits, which are crucial for planning the project effectively. References: PRINCE2 Foundation official documentation and study materials.


NEW QUESTION # 143
What is performed as part of the recommended risk management procedure?

  • A. A budget to investigate issues is allocated
  • B. Risk management practices are reviewed to ensure that they are performed effectively
  • C. Conflicts between the project and the programme board are resolved
  • D. Information about risks to the projects is sent to project stakeholders

Answer: B

Explanation:
As part of the recommended risk management procedure in PRINCE2, it is essential to regularly review risk management practices to ensure their effectiveness. This involves evaluating how risks are identified, assessed, and controlled throughout the project lifecycle. References: PRINCE2 Foundation Handbook, Risk Management section.


NEW QUESTION # 144
Which is an objective of the 'managing a product delivery' process?

  • A. To ensure the business case is regularly reviewed
  • B. To request authorization to start the next stage
  • C. To deliver the planned specialist products within tolerance
  • D. To assess whether the stage products have been approved

Answer: C

Explanation:
Section: Volume B
Explanation/Reference: http://prince2.wiki/Managing_Product_Delivery#Objective


NEW QUESTION # 145
How should the 'progress' practice be used?

  • A. To identify opportunities that may make the project more successful
  • B. To deliver change which will benefit people in their day-to-day work
  • C. To predict whether the benefits will exceed the costs
  • D. To define how the products will be delivered to enable control

Answer: C

Explanation:
The 'progress' practice in PRINCE2 should be used to monitor and control the performance of the project against its plans and the project's overall direction. This includes predicting whether the benefits will exceed the costs, which is crucial for evaluating the project's ongoing viability and justifying the continuation of the project based on its forecasted value to the organization.References: (PRINCE2 7 Foundation Handbook, AXELOS)


NEW QUESTION # 146
How many tasks does the product-based planning technique describe?

  • A. Four
  • B. Three
  • C. One
  • D. Two

Answer: A

Explanation:
The product-based planning technique described in PRINCE2 involves four tasks: writing the Project Product Description, creating the product breakdown structure, writing product descriptions, and creating the product flow diagram. These tasks collectively help in planning the project by focusing on the products that will be delivered. References: PRINCE2 Foundation manual, PRINCE2 official resources


NEW QUESTION # 147
Identify the missing word(s) in the following sentence:
[ ? ] dependency is one between two products of a project, over which the project team has control.

  • A. A schedule-driven
  • B. An external
  • C. An internal
  • D. A resource-driven

Answer: C

Explanation:
In PRINCE2, an 'internal' dependency refers to a relationship between two products of a project that is under the control of the project team. These dependencies are managed within the project's boundaries, unlike external dependencies which involve elements outside the project's direct control.References: PRINCE2 7 Foundation materials on product dependencies.


NEW QUESTION # 148
Which role is part of the project management team?

  • A. Stakeholder
  • B. Quality assurance
  • C. Corporate or programme management
  • D. Change Authority

Answer: D


NEW QUESTION # 149
Thea project manager needs to report to the project board on the status of the project's issues.
Which management product should the project manager review?

  • A. Checkpoint report
  • B. Highlight report
  • C. Project brief
  • D. Project log

Answer: B

Explanation:
The Project Manager should review the Highlight Report to report to the Project Board on the status of the project's issues. The Highlight Report provides a regular summary of the stage status, including progress against the plan and details about any issues or risks, making it the appropriate management product for communicating current issues to the Project Board.
(PRINCE2 7 Foundation Handbook, AXELOS)


NEW QUESTION # 150
What is a benefits management approach used to assess?

  • A. How the project has progressed against its plans
  • B. How the project's products have performed when in operational use
  • C. The suitability of the project management team structure
  • D. The effectiveness of the project strategies

Answer: B

Explanation:
Explanation
Reference https://mplaza.pm/prince2-benefits-management-approach-template/


NEW QUESTION # 151
Which of the following refers to the actions identified to bring a situation to a level where exposure to a risk is acceptable?

  • A. Risk response
  • B. Risk category
  • C. Risk description
  • D. Risk status

Answer: A


NEW QUESTION # 152
Which is a purpose of the Starting up a Project process?

  • A. Define the means of communication between the project and corporate or programme management
  • B. Provide information so a decision can be made asto whether a project is viable and worthwhile to initiate
  • C. Record any identified risks in the Risk Register
  • D. Define the project controls

Answer: B


NEW QUESTION # 153
Identify the missing words in the following sentence. At the end of a stage, the [ ? ] should be used to check whether there is a requirement to send copies of the End Stage Report to external interested parties.

  • A. Quality Management Strategy
  • B. Stage Plan
  • C. Follow-on action recommendations
  • D. Communication Management Strategy

Answer: D

Explanation:
Section: Volume A


NEW QUESTION # 154
......


PRINCE2 Foundation written exam serves as a prerequisite for the PRINCE2 Practitioner exam, and it focuses on providing the basic principles, terminology, and processes of the PRINCE2 methodology. EXIN PR2F certification is essential for professionals who seek to understand the PRINCE2 methodology and its application to project management. Furthermore, it demonstrates their ability to work within a PRINCE2 environment effectively.


PRINCE2-Foundation certification exam is a widely recognized credential in the project management field. PRINCE2 stands for Projects IN Controlled Environments, and it is a framework for managing projects. The PRINCE2 Foundation written exam is designed to test the candidate's knowledge and understanding of the PRINCE2 methodology.

 

Online Questions - Valid Practice PRINCE2-Foundation Exam Dumps Test Questions: https://www.pass4training.com/PRINCE2-Foundation-pass-exam-training.html

100% Real PRINCE2-Foundation dumps  - Brilliant PRINCE2-Foundation Exam Questions PDF: https://drive.google.com/open?id=1F801T8kePVp8J7YzZpZdeUIFkfoLGFiq